A petrol station was in the process of removing one of their plant rooms and replacing it with new pipework. A minor underground leak had caused issues, so they were proactive in sourcing a replacement. However, it would be several weeks until this work was complete, so they needed the expertise and skills of Ideal Heat Solutions to provide a boiler that was ready and in situ if the minor leak was to burst.

The 1.2Mw temporary boiler plant room we installed was used to heat the building for 8 weeks, whilst the new pipework was being fitted. It provided constant heat throughout the three-story building for its full time at the site.
Even after they had a new system in place, a petrol station opted to keep our temporary boiler in place for a further three weeks, ensuring that there was a reliable back up if their new boiler room plant encountered any issues.

The client was satisfied by the speed at which Ideal Heat Solutions responded to the problem, and the professionalism displayed throughout the process. They praised our engineers for making themselves available at any time to respond to call-outs, making every effort to maintain a fully functioning boiler for their site.